City of San Carlos - 2017
Below are the activities that have occurred in 2017 concerning PG&E Line 147 safety issues. See the news releases for more details.
January PG&E continues repair work along Line 147 along private property west of Alameda de las Pulgas. 
June        PG&E completed the work along Line 147 in Spring 2017. PG&E will hold a public meeting on June 27, 2017 to discuss the project and next steps with the community. PG&E asked the CPUC to allow it to re-pressurize the line. That decision is still pending.