Fiscal Implications:
Following are estimated project costs for each alternative:
| Natural Turf: | |
| a. Design and bidding process | $60,000.00 |
| b. Construction and construction management | $386,000.00 |
Total
| $446,000.00 |
| Synthetic Turf: | |
| a. Environmental Document | $60,000.00 |
| b. Design and Bidding process | $71,000.00 |
| c. Construction and construction management | $1,426,000.00 |
Total
| $1,557,000.00 |
The Capital Improvement Program (CIP) budget adopted by the City Council at its regular meeting of June 11, 2007 provides $90,000 for the design of the project in fiscal year 2007/2008 and $1,700,000, including $500,000 in anticipated donations, for final construction of the project in fiscal year 2008/2009.Staff has estimated that approximately $1,200,000 of in-lieu park dedication and park impact fees will be paid to the City by developers within the next 12 months. The $500,000 in donations may be derived from community fund raising or a contribution from the District. The City may wish to consider making a formal request of the District for a funding contribution for either of the options listed above.
Background:
The City Council authorized issuance of a Request for Proposal for design and preparation of plans, specifications and cost estimates for installation of a natural or synthetic turf at Heather School Athletic Field, including a comparative analysis of each turf type at its regular meeting of December 11, 2006.The RFP was prepared and distributed to six qualified consultants.Three firms submitted proposals for design development and preparation of construction documents. After thorough analysis by Public Works and Parks and Recreation staff, the Callendar proposal was rated the most responsive with the best detailed analysis for both alternatives.Following two interviews with the principal of the firm and his project team, staff negotiated fees and the proposed schedules.
The Callander comparative analysis of natural and synthetic turf athletic fields is provided in Attachment 4.Staff believes that the City may enter into an agreement with Callendar for services as proposed if the Natural Turf option is selected.Staff believes an alternative and more limited agreement with Callendar would be appropriate (i.e., for assistance in conducting the appropriate environmental review) if the Council prefers to pursue the Synthetic Turf option.
Implementation Schedule
Following is a tentative implementation timeline for each alternative:
Natural Turf
Implementation would follow execution of a long term lease agreement with the District and authorization for Callander to proceed with design.
- Design and preparation of construction documents
| 110 days |
- Bidding process and award of contract
| 60 days |
| 90 days |
| 10 days |
| 30 days |
Total
| 300 days |
Synthetic Turf
Implementation would follow execution of a long term lease agreement with the District.Project approval, design and final funding considerations would be subject to the results of appropriate environmental review.
- Preparation and release of RFP for environmental document
| 30 days |
- Preparation of proposals by consultants
| 30 days |
- Review of proposals and selection of consultants
| 15 days |
- Execution of Professional Services Agreement
| 10 days |
- Preparation of the environmental document
| 150 days |
- Certification of the environmental document
| 65 days |
- Design and preparation of construction documents
| 115 days |
- Bidding process and award of contract
| 60 days |
| 90 days |
Total
| 565 days |
Alternatives:The alternatives available to the City Council include:
1. Authorize an agreement with Callander Associates Architecture, Inc. for services associated with renovation of Heather School Athletic Field with Natural Turf; or
2. Authorize a revised agreement with Callendar Associates Architecture, Inc. for services associated with possible renovation of Heather School Athletic Field with Synthetic Turf;
3. Do not approve agreements for renovation of Heather Field; or
4. Provide staff with alternative direction.
Respectfully submitted,
Barry Weiss, Director of Parks and Recreation
Parviz Mokhtari, Director of Public Works
Approved for submission by:
Mark Weiss, City Manager
Attachments: