2023 Annual Storm Drain Improvement Project
1000 Drake Court, San Carlos, CA94070
1000 Drake Court San Carlos San Carlos, CA 94070
1005 Drake Court San Carlos San Carlos, CA 94070
3017 Brittan Avenue San Carlos, CA 94070
261 El Camino Real San Carlos, CA 94070
CATEGORIES:
- Public Works Map Projects
C9531
Project Description
This project includes removing and installing new headwalls, storm concrete channel, removing and installing storm pipes, removing and installing storm drain inlets, rip-rap, erosion control to improve stormwater capture in addition to preventing trash and debris from entering the storm drain system.
Project Area
There are four locations that will be improved as part of the project:
- 1000 Drake Court;
- 1005 Drake Court
- 3017 Brittan Avenue; and
- 261 El Camino Real
Tentative schedule shown below:
PROJECT LOCATION: | DATE(S): | DESCRIPTION OF WORK: |
1000 Drake Ct | 8/23 | Remove Shed |
8/28 | Install Temp. Fence | |
8/29 | Mobilize Equipment; Clear & Grub; Pothole Existing Storm | |
8/30 - 8/31 | Excavate to Subgrade | |
9/1 - 9/5 | Install 15" Storm | |
9/5 -11/6 | Concrete Work | |
9/5 - 10/24 | Weir Structure | |
9/8 - 10/23 | Concrete Work | |
10/4 - 10/16 | Solder Pile Wall | |
10/16 - 10/24 | Install 15" Storm Pipe | |
10/26 | Connect Pipe | |
11/1 - 11/2 | Build Earthen Wall | |
11/3 - 11/6 | Install Rip Rap | |
11/7 - 11/9 | Build AB Path | |
11/13 | Fine Grade and Seed | |
11/14 - 11/15 | Install Erosion Control | |
1005 Drake Ct | 8/21 | Install Temp. Fence; Demo Existing Structure; Excavate for New Structure |
8/22 - 8/29 | F / R / P Structure | |
8/30 - 9/5 | Cure & Strip | |
9/8 | Excavate to Subgrade | |
9/12 - 9/15 | Install Rip Rap | |
3017 Brittan Ave | 8/21 - 8/22 | Install Temp. Fence |
8/22 | Mobilize Equipment | |
8/23 | Clear & Grub; Create Access Path | |
8/24 - 9/1 | Excavate for Structure & Catch Basin | |
9/1 - 9/29 | Off-haul Dirt | |
9/5 - 11/6 | Concrete Work | |
9/5 - 10/30 | Weir Structure | |
11/1 - 11/8 | Backfill | |
11/9 - 11/14 | Build AB Road | |
11/15 - 11/20 | Install Rip Rap | |
11/21 - 11/22 | Fine Grade and Seed | |
11/27 - 11/28 | Install Erosion Control Blanket | |
261 El Camino Real | 8/29 - 9/12 | Procure Caltrans Permit |
10/18 - 10/25 | Install 24" Storm | |
10/27 - 10/30 | Restore Trench | |
10/31 | Paving | |
11/1 | Pour Sidewalk |
Working Hours: Monday through Friday between 8:00a.m. and 4:00 p.m.
Public Impact
Traffic Control: Residents should expect minor traffic control around the work areas.
Noise: Residents should expect noise during the work from the construction equipment used due to the nature of the project.
Category
- Capital Improvement Project
- City of San Carlos (City Department)
JMB Construction, Inc.
Stephen Campbell
(415) 559-7642
City of San Carlos Contact
Vatsal Patel
Senior Engineer
vpatel@cityofsancarlos.org
(650) 802-4202