2023 Annual Storm Drain Improvement Project

C9531

Project Description

This project includes removing and installing new headwalls, storm concrete channel, removing and installing storm pipes, removing and installing storm drain inlets, rip-rap, erosion control to improve stormwater capture in addition to preventing trash and debris from entering the storm drain system. 


Project Area

There are four locations that will be improved as part of the project:
2023 Annual Storm Drain Improvement Cover Picture

  1. 1000 Drake Court; 
  2. 1005 Drake Court
  3. 3017 Brittan Avenue; and
  4. 261 El Camino Real
Project Duration

Tentative schedule shown below:
PROJECT LOCATION: DATE(S): DESCRIPTION OF WORK:
1000 Drake Ct     8/23  Remove Shed
  8/28 Install Temp. Fence
  8/29 Mobilize Equipment; Clear & Grub; Pothole Existing Storm
  8/30 - 8/31 Excavate to Subgrade
  9/1 - 9/5 Install 15" Storm
  9/5 -11/6 Concrete Work
  9/5 - 10/24 Weir Structure
  9/8 - 10/23  Concrete Work
  10/4 - 10/16 Solder Pile Wall
  10/16 - 10/24 Install 15" Storm Pipe
  10/26 Connect Pipe
  11/1 - 11/2 Build Earthen Wall
  11/3 - 11/6 Install Rip Rap
  11/7 - 11/9 Build AB Path
  11/13 Fine Grade and Seed
  11/14 - 11/15 Install Erosion Control
1005 Drake Ct  8/21 Install Temp. Fence; Demo Existing Structure; Excavate for New Structure
  8/22 - 8/29 F / R / P Structure 
  8/30 - 9/5 Cure & Strip
  9/8  Excavate to Subgrade
  9/12 - 9/15 Install Rip Rap
3017 Brittan Ave  8/21 - 8/22 Install Temp. Fence
  8/22 Mobilize Equipment
  8/23 Clear & Grub; Create Access Path
  8/24 - 9/1 Excavate for Structure & Catch Basin
  9/1 - 9/29 Off-haul Dirt
  9/5 - 11/6 Concrete Work
  9/5 - 10/30 Weir Structure
  11/1 - 11/8 Backfill
  11/9 - 11/14 Build AB Road
  11/15 - 11/20 Install Rip Rap
  11/21 - 11/22 Fine Grade and Seed
  11/27 - 11/28 Install Erosion Control Blanket
261 El Camino Real 8/29 - 9/12 Procure Caltrans Permit
  10/18 - 10/25  Install 24" Storm
  10/27 - 10/30 Restore Trench
  10/31 Paving
  11/1 Pour Sidewalk

Working Hours: Monday through Friday between 8:00a.m. and 4:00 p.m.                                                 

Public Impact

Traffic Control: Residents should expect minor traffic control around the work areas.

Noise: Residents should expect noise during the work from the construction equipment used due to the nature of the project. 

Category

  • Capital Improvement Project
Project Ownership

  • City of San Carlos (City Department)
Contractor Information

JMB Construction, Inc.
Stephen Campbell
(415) 559-7642

City of San Carlos Contact

Vatsal Patel
Senior Engineer
vpatel@cityofsancarlos.org
(650) 802-4202

Sign Up For E-NEWS